DELIVERY RECORDS · DUBAI
Azizi Developments Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Azizi Developments's company profile and catalogue projects ↗
83 half-year comparisons · 1 additional completed-project records. Original comparison research: 31 Aug 2026.
- Azizi Aliyah Residences2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1799
- Azizi Amber2025 H22024 H2★EarlierTarget sourceDLD 100% record #2624
- Azizi Aura Residences2020 H22020 H2Same half-yearTarget sourceDLD 100% record #1897
- Azizi Berton2023 H22023 H2Same half-yearTarget sourceDLD 100% record #1918
- Azizi Farishta Residence2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1810
- Azizi Gardens2022 H12023 H2About 12–18 months lateTarget sourceDLD 100% record #2037
- Azizi Greenfield2022 H12024 H1About 18–24 months lateTarget sourceDLD 100% record #2035
- Azizi Mina2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1771
- Azizi Park Avenue2024 H12024 H1Same half-yearTarget sourceDLD 100% record #2038
- Azizi Pearl2024 H12024 H1Same half-yearTarget sourceDLD 100% record #1917
- Azizi Plaza Hotel Apartments2021 H22021 H2Same half-yearTarget sourceDLD 100% record #1789
- Azizi Riviera 12024 H22024 H2Same half-yearTarget sourceDLD 100% record #1958
- Azizi Riviera 102022 H22022 H2Same half-yearTarget sourceDLD 100% record #1993
- Azizi Riviera 112022 H22022 H2Same half-yearTarget sourceDLD 100% record #1974
- Azizi Riviera 122022 H22022 H2Same half-yearTarget sourceDLD 100% record #1972
- Azizi Riviera 132021 H22022 H2About 6–12 months lateTarget sourceDLD 100% record #1976
- Azizi Riviera 142023 H12023 H1Same half-yearTarget sourceDLD 100% record #1994
- Azizi Riviera 152022 H12023 H2About 12–18 months lateTarget sourceDLD 100% record #1975
- Azizi Riviera 162022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #1928
- Azizi Riviera 172022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #2046
- Azizi Riviera 182023 H22023 H2Same half-yearTarget sourceDLD 100% record #1996
- Azizi Riviera 192023 H22023 H2Same half-yearTarget sourceDLD 100% record #2002
- Azizi Riviera 22022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #1955
- Azizi Riviera 202022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #1966
- Azizi Riviera 212023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #1965
- Azizi Riviera 222023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2003
- Azizi Riviera 232022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #2009
- Azizi Riviera 242023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2120
- Azizi Riviera 252023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2230
- Azizi Riviera 262023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2119
- Azizi Riviera 272023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2121
- Azizi Riviera 282023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2118
- Azizi Riviera 292023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2122
- Azizi Riviera 32024 H12024 H1Same half-yearTarget sourceDLD 100% record #1951
- Azizi Riviera 302023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2123
- Azizi Riviera 312023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2231
- Azizi Riviera 322023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2042
- Azizi Riviera 332023 H22023 H2Same half-yearTarget sourceDLD 100% record #2040
- Azizi Riviera 342023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2043
- Azizi Riviera 352021 H22023 H2About 18–24 months lateTarget sourceDLD 100% record #2041
- Azizi Riviera 362024 H12024 H1Same half-yearTarget sourceDLD 100% record #2340
- Azizi Riviera 372024 H12024 H1Same half-yearTarget sourceDLD 100% record #2048
- Azizi Riviera 382024 H12024 H1Same half-yearTarget sourceDLD 100% record #2051
- Azizi Riviera 392024 H12024 H1Same half-yearTarget sourceDLD 100% record #2124
- Azizi Riviera 42022 H22022 H2Same half-yearTarget sourceDLD 100% record #1942
- Azizi Riviera 402022 H12024 H1About 18–24 months lateTarget sourceDLD 100% record #2125
- Azizi Riviera 412024 H12024 H1Same half-yearTarget sourceDLD 100% record #2343
- Azizi Riviera 422024 H12024 H1Same half-yearTarget sourceDLD 100% record #2341
- Azizi Riviera 432024 H12024 H1Same half-yearTarget sourceDLD 100% record #2342
- Azizi Riviera 442024 H12024 H1Same half-yearTarget sourceDLD 100% record #2296
- Azizi Riviera 452024 H12024 H1Same half-yearTarget sourceDLD 100% record #2295
- Azizi Riviera 462024 H12024 H1Same half-yearTarget sourceDLD 100% record #2294
- Azizi Riviera 472024 H12024 H1Same half-yearTarget sourceDLD 100% record #2398
- Azizi Riviera 482022 H12024 H1About 18–24 months lateTarget sourceDLD 100% record #2126
- Azizi Riviera 52023 H12023 H1Same half-yearTarget sourceDLD 100% record #1927
- Azizi Riviera 592025 H12025 H1Same half-yearTarget sourceDLD 100% record #2658
- Azizi Riviera 62022 H22022 H2Same half-yearTarget sourceDLD 100% record #1956
- Azizi Riviera 612025 H12025 H1Same half-yearTarget sourceDLD 100% record #2817
- Azizi Riviera 632025 H12025 H1Same half-yearTarget sourceDLD 100% record #2686
- Azizi Riviera 652025 H12025 H1Same half-yearTarget sourceDLD 100% record #2742
- Azizi Riviera 672025 H12025 H1Same half-yearTarget sourceDLD 100% record #2912
- Azizi Riviera 72022 H22022 H2Same half-yearTarget sourceDLD 100% record #1940
- Azizi Riviera 82023 H12023 H1Same half-yearTarget sourceDLD 100% record #1995
- Azizi Riviera 92023 H12023 H1Same half-yearTarget sourceDLD 100% record #2068
- Azizi Riviera Azure2025 H22025 H2Same half-yearTarget sourceDLD 100% record #2508
- Azizi Samia Residence2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1814
- Azizi Shaista Residence2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1783
- Azizi Star Hotel Apartments2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1822
- Azizi Vista2025 H12025 H2About 0–6 months lateTarget sourceDLD 100% record #2650
- Azizi. Daisy2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1572
- Azizi. Feirouz2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1509
- Azizi. Freesia2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1573
- Azizi. Iris2015 H22017 H1About 12–18 months lateTarget sourceDLD 100% record #1512
- Azizi. Liatris2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1511
- Azizi. Orchid2016 H22017 H1About 0–6 months lateTarget sourceDLD 100% record #1513
- Azizi. Yasamine2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1510
- Candace Acacia Hotel Apartments2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1737
- Candace Aster Hotel Apartments2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1738
- Farhad Azizi Residence2022 H22022 H2Same half-yearTarget sourceDLD 100% record #1914
- Fawad Azizi Residence2022 H12024 H1About 18–24 months lateTarget sourceDLD 100% record #2088
- Montrell Hotel Aprtments2018 H12019 H2About 12–18 months lateTarget sourceDLD 100% record #1763
- Roy Mediterranean Hotel Apartments2018 H12018 H1Same half-yearTarget sourceDLD 100% record #1762
- Royal Bay2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1721
Additional completed-project records
Marked FINISHED at 100% in the DLD snapshot of 15 Jun 2026. Comparable target and technical-completion periods have not yet been established; no timing category is assigned.
- Azizi TulipDLD #1574 · Completed in snapshotDLD project data ↗
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.