Deyaar Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Deyaar's company profile and catalogue projects ↗
6 half-year comparisons · 13 additional completed-project records. Original comparison research: 31 Aug 2026.
- Midtown - Afnan2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1672
- Midtown - Dania2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1731
- Midtown - Mesk2022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2211
- Midtown - Noor2023 H12023 H1Same half-yearTarget sourceDLD 100% record #2210
- Montrose2018 H12018 H1Same half-yearTarget sourceDLD 100% record #1537
- The Atria2018 H12018 H2About 0–6 months lateTarget sourceDLD 100% record #1483
Additional completed-project records
Marked FINISHED at 100% in the DLD snapshot of 15 Jun 2026. Comparable target and technical-completion periods have not yet been established; no timing category is assigned.
- Coral ResidenceDLD #43 · Completed in snapshotDLD project data ↗
- Mayfair ResidencyDLD #52 · Completed in snapshotDLD project data ↗
- Fairview ResidencyDLD #57 · Completed in snapshotDLD project data ↗
- Jade ResidenceDLD #55 · Completed in snapshotDLD project data ↗
- Mayfair TowerDLD #53 · Completed in snapshotDLD project data ↗
- Oakwood ResidencyDLD #47 · Completed in snapshotDLD project data ↗
- Al Seef 1DLD #42 · Completed in snapshotDLD project data ↗
- Ruby ResidenceDLD #50 · Completed in snapshotDLD project data ↗
- Al Seef 2DLD #48 · Completed in snapshotDLD project data ↗
- Sapphire ResidenceDLD #49 · Completed in snapshotDLD project data ↗
- Madison ResidencyDLD #54 · Completed in snapshotDLD project data ↗
- Clayton ResidencyDLD #60 · Completed in snapshotDLD project data ↗
- Hamilton ResidencyDLD #56 · Completed in snapshotDLD project data ↗
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.