DELIVERY RECORDS · DUBAI

Binghatti Project Handover Comparisons

Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.

Explore Binghatti's company profile and catalogue projects ↗
30 half-year comparisons · 4 additional completed-project records. Original comparison research: 31 Aug 2026.

EarlierSame half-year0–6 months late6–12 months late12+ months late
ProjectAvailable delivery targetDLD 100% technical completionApproximate differenceSources
  1. Binghatti Amber2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2673
  2. Binghatti Avenue2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2185
  3. Binghatti Azure2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2862
  4. Binghatti Canal2023 H12023 H1Same half-yearTarget sourceDLD 100% record #2366
  5. Binghatti Corner2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2478
  6. Binghatti Creek2023 H12023 H1Same half-yearTarget sourceDLD 100% record #2361
  7. Binghatti Crescent2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2535
  8. Binghatti Crest2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2473
  9. Binghatti Emerald2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2571
  10. Binghatti Gardenia2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2662
  11. Binghatti Gate2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2232
  12. Binghatti Gateway2021 H12021 H2About 0–6 months lateTarget sourceDLD 100% record #2117
  13. Binghatti Gems2022 H12022 H2About 0–6 months lateTarget sourceDLD 100% record #2271
  14. Binghatti Heights2023 H22024 H1About 0–6 months lateTarget sourceDLD 100% record #2415
  15. Binghatti House2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2670
  16. Binghatti Jasmine2023 H12022 H2EarlierTarget sourceDLD 100% record #2386
  17. Binghatti Lavender2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2825
  18. Binghatti Luna2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2441
  19. Binghatti Mirage2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2233
  20. Binghatti Nova2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2494
  21. Binghatti Onyx2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2610
  22. Binghatti Point2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2203
  23. Binghatti Rose2022 H12022 H2About 0–6 months lateTarget sourceDLD 100% record #2326
  24. Binghatti Stars2019 H22020 H1About 0–6 months lateTarget sourceDLD 100% record #1933
  25. Binghatti Venus2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2671
  26. Binghatti Views2017 H12017 H1Same half-yearTarget sourceDLD 100% record #1689
  27. Dawn By Binghatti2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #3023
  28. Dusk By Binghatti2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #3024
  29. Millennium Binghatti Residences Business Bay2021 H12021 H2About 0–6 months lateTarget sourceDLD 100% record #2014
  30. Trillionaire Residences By Binghatti2024 H12025 H1About 6–12 months lateTarget sourceDLD 100% record #2643

Additional completed-project records

Marked FINISHED at 100% in the DLD snapshot of 15 Jun 2026. Comparable target and technical-completion periods have not yet been established; no timing category is assigned.

Read delivery history project by project

  1. Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
  2. Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
  3. Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?

No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.

Is the developer with the most early entries the safest?

This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.

Return to project-level research