DELIVERY RECORDS · DUBAI
Nshama Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Nshama's company profile and catalogue projects ↗
18 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.
- Ascot Residences2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2523
- Hayat Boulevard2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1755
- Liva2025 H22025 H1★EarlierTarget sourceDLD 100% record #2492
- Maha Townhouses2025 H22025 H1★EarlierTarget sourceDLD 100% record #2490
- Naseem Townhouses2020 H22020 H2Same half-yearTarget sourceDLD 100% record #1936
- Noor Townhouses2020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1823
- Rawda Apartments2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1836
- Reem Townhouses2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2289
- Safi Townhouses2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1787
- Sama Townhouses2021 H12021 H2About 0–6 months lateTarget sourceDLD 100% record #2084
- Shams Townhouses2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2405
- The Diplomat Residences2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2524
- The Regent2025 H22025 H1★EarlierTarget sourceDLD 100% record #2525
- Town Square Hayat2017 H22018 H1About 0–6 months lateTarget sourceDLD 100% record #1638
- Town Square Jenna And Warda2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1677
- Town Square Safi2018 H12019 H1About 6–12 months lateTarget sourceDLD 100% record #1646
- Town Square Zahra2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1637
- Una2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1979
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.