DELIVERY RECORDS · DUBAI
Meydan Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Meydan's company profile and catalogue projects ↗
40 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.
- Canal Front Residences Cf1 & Cf22024 H12024 H1Same half-yearTarget sourceDLD 100% record #2315
- Canal Front Residences-Cf3&Cf42024 H12024 H1Same half-yearTarget sourceDLD 100% record #2333
- Canal Front Residences-Cf5&Cf62024 H22024 H2Same half-yearTarget sourceDLD 100% record #2364
- Canal Front Residences-Cf7 & Cf8 & Cf92024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2363
- Lagoon Views At District One2025 H12025 H1Same half-yearTarget sourceDLD 100% record #2310
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , A Villas2023 H22024 H1About 0–6 months lateTarget sourceDLD 100% record #2256
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 12022 H12022 H1Same half-yearTarget sourceDLD 100% record #1984
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 112023 H22024 H1About 0–6 months lateTarget sourceDLD 100% record #2226
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 132023 H22023 H2Same half-yearTarget sourceDLD 100% record #2162
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 142023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2024
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 152022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #1998
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 162019 H22023 H1About 36–42 months lateTarget sourceDLD 100% record #1997
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 172022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2237
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 182022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2238
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 192022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2245
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 22022 H12022 H1Same half-yearTarget sourceDLD 100% record #2001
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 202023 H12023 H1Same half-yearTarget sourceDLD 100% record #2246
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 212022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2247
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 222023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2242
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 232023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2243
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 242023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2248
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 252023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2249
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 262023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2250
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 272023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2251
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 282023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2253
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 292023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2244
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 32022 H12022 H1Same half-yearTarget sourceDLD 100% record #2000
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 302023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2254
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 312022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #2252
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 42021 H12022 H1About 6–12 months lateTarget sourceDLD 100% record #1703
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 52022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #1999
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 62023 H22023 H2Same half-yearTarget sourceDLD 100% record #2170
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 72023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2241
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 82023 H22023 H2Same half-yearTarget sourceDLD 100% record #2225
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences122023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2091
- Mohammed Bin Rashid Al Maktoum City District One B Extension Villas2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2269
- Mohammed Bin Rashid Al Maktoum City District One- C Villas2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2267
- Mohammed Bin Rashid Al Maktoum City District One, B Villas2024 H12025 H1About 6–12 months lateTarget sourceDLD 100% record #2266
- Mohammed Bin Rashid Al Maktoum City- District One, Phase 12020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1366
- Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas2020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1496
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.