Danube Properties Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Danube Properties's company profile and catalogue projects ↗
17 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.
- Bayz Tower2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1889
- Dreamz2016 H12018 H1About 18–24 months lateTarget sourceDLD 100% record #1534
- Elz Residence2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2115
- Gemz By Danube2025 H12024 H2★EarlierTarget sourceDLD 100% record #2395
- Glamz Residence2020 H22020 H2Same half-yearTarget sourceDLD 100% record #1749
- Glitz Residence 12017 H22017 H2Same half-yearTarget sourceDLD 100% record #1614
- Glitz Residence 22017 H22017 H2Same half-yearTarget sourceDLD 100% record #1615
- Glitz Residence 32017 H22018 H2About 6–12 months lateTarget sourceDLD 100% record #1655
- Jewelz Residence2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2027
- Lawnz Residence By Danube2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2073
- Miraclz Tower2019 H22021 H1About 12–18 months lateTarget sourceDLD 100% record #1819
- Olivz Residence2023 H22024 H1About 0–6 months lateTarget sourceDLD 100% record #2215
- Opalz By Danube2025 H12025 H1Same half-yearTarget sourceDLD 100% record #2465
- Pearlz By Danube2025 H12024 H1★EarlierTarget sourceDLD 100% record #2376
- Resortz Residence2019 H22020 H1About 0–6 months lateTarget sourceDLD 100% record #1852
- Starz Tower By Danube2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1699
- Wavez Residence2021 H12023 H2About 24–30 months lateTarget sourceDLD 100% record #2175
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.