DELIVERY RECORDS · DUBAI

Meraas Project Handover Comparisons

Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.

Explore Meraas's company profile and catalogue projects ↗
27 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.

EarlierSame half-year0–6 months late6–12 months late12+ months late
ProjectAvailable delivery targetDLD 100% technical completionApproximate differenceSources
  1. Asayel At Madinat Jumeirah Living2023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2146
  2. Bulgari Ocean Mansions2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2331
  3. Bv Mansions2018 H12018 H1Same half-yearTarget sourceDLD 100% record #1815
  4. Bv Residences2016 H22018 H1About 12–18 months lateTarget sourceDLD 100% record #1650
  5. Celadon2024 H22025 H2About 6–12 months lateTarget sourceDLD 100% record #2325
  6. Central Park At City Walk -Building 12021 H22024 H2About 30–36 months lateTarget sourceDLD 100% record #2147
  7. Jadeel -Madinat Jumeirah Living2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2369
  8. La Rive2022 H22022 H2Same half-yearTarget sourceDLD 100% record #2131
  9. Madinat Jumeirah Living2021 H12021 H1Same half-yearTarget sourceDLD 100% record #2097
  10. Madinat Jumeriah Living - Phase 22021 H12022 H1About 6–12 months lateTarget sourceDLD 100% record #2116
  11. Myrtle2025 H12025 H2About 0–6 months lateTarget sourceDLD 100% record #2381
  12. No. 4a, No.4b, No.5 Citywalk Residential2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1718
  13. No. 6a And No.6b Citywalk Residential2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1720
  14. No.1, No.2a, No.2b, No.3a And 3b Citywalk Residential2017 H12016 H2EarlierTarget sourceDLD 100% record #1719
  15. No.15 & No.16 Citywalk Residential2017 H12017 H1Same half-yearTarget sourceDLD 100% record #1754
  16. No.17, No.18a,No.18b And No.19 Citywalk Residential2017 H12017 H2About 0–6 months lateTarget sourceDLD 100% record #1781
  17. No.20, No.21a, No.21b And No.22 Citywalk Residential2017 H12017 H1Same half-yearTarget sourceDLD 100% record #1736
  18. No.23a And 23b Citywalk Residential2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1780
  19. No.9 & No.10 Citywalk Residential2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1717
  20. Port De La Mer - La Cote2021 H22021 H2Same half-yearTarget sourceDLD 100% record #2093
  21. Port De La Mer - La Sirene2024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2264
  22. Port De La Mer - La Sirene 22024 H12024 H2About 0–6 months lateTarget sourceDLD 100% record #2299
  23. Port De La Mer - La Voile2022 H12023 H1About 6–12 months lateTarget sourceDLD 100% record #2181
  24. Port De La Mer - Le Pont2022 H22022 H2Same half-yearTarget sourceDLD 100% record #2153
  25. Sur La Mer2021 H22023 H2About 18–24 months lateTarget sourceDLD 100% record #2167
  26. Sur La Mer 22022 H22022 H2Same half-yearTarget sourceDLD 100% record #2169
  27. Viridian2024 H22025 H2About 6–12 months lateTarget sourceDLD 100% record #2324

Read delivery history project by project

  1. Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
  2. Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
  3. Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?

No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.

Is the developer with the most early entries the safest?

This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.

Return to project-level research