DELIVERY RECORDS · DUBAI

Nakheel Project Handover Comparisons

Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.

Explore Nakheel's company profile and catalogue projects ↗
16 half-year comparisons · 4 additional completed-project records. Original comparison research: 31 Aug 2026.

EarlierSame half-year0–6 months late6–12 months late12+ months late
ProjectAvailable delivery targetDLD 100% technical completionApproximate differenceSources
  1. Alfurjan Package 42016 H22017 H1About 0–6 months lateTarget sourceDLD 100% record #1686
  2. Alfurjan Package 62016 H22017 H1About 0–6 months lateTarget sourceDLD 100% record #1661
  3. Azure Residence2015 H22016 H2About 6–12 months lateTarget sourceDLD 100% record #1350
  4. Club Vista Mare2015 H12016 H2About 12–18 months lateTarget sourceDLD 100% record #1351
  5. Jumeirah Park 7a2015 H22019 H1About 36–42 months lateTarget sourceDLD 100% record #1369
  6. Jumeirah Park 7b&C2016 H12018 H2About 24–30 months lateTarget sourceDLD 100% record #1368
  7. Jumeirah Park Package 1a2015 H22015 H2Same half-yearTarget sourceDLD 100% record #1485
  8. Murooj Al Furjan 12024 H22024 H1EarlierTarget sourceDLD 100% record #2261
  9. Murooj Al Furjan 22024 H22024 H1EarlierTarget sourceDLD 100% record #2262
  10. Murooj Alfurjan West2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2273
  11. The Palm Tower2021 H22022 H1About 0–6 months lateTarget sourceDLD 100% record #1603
  12. Tilal Al Furjan- Phase One2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2338
  13. Tilal Al Furjan- Phase Two2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2337
  14. Warsan Village - B & C2016 H12017 H1About 6–12 months lateTarget sourceDLD 100% record #1385
  15. Warsan Village - D2016 H12017 H1About 6–12 months lateTarget sourceDLD 100% record #1386
  16. Warsan Village A2016 H12017 H1About 6–12 months lateTarget sourceDLD 100% record #1384

Additional completed-project records

Marked FINISHED at 100% in the DLD snapshot of 15 Jun 2026. Comparable target and technical-completion periods have not yet been established; no timing category is assigned.

Read delivery history project by project

  1. Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
  2. Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
  3. Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?

No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.

Is the developer with the most early entries the safest?

This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.

Return to project-level research