DELIVERY RECORDS · DUBAI

Dubai South Properties Project Handover Comparisons

Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.

Explore Dubai South Properties's company profile and catalogue projects ↗
13 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.

EarlierSame half-year0–6 months late6–12 months late12+ months late
ProjectAvailable delivery targetDLD 100% technical completionApproximate differenceSources
  1. The Pulse Beachfront 22024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2328
  2. The Pulse Beachfront 32025 H12025 H1Same half-yearTarget sourceDLD 100% record #2367
  3. The Pulse Boulevard Apartments2019 H22020 H1About 0–6 months lateTarget sourceDLD 100% record #1806
  4. The Pulse Boulevard Apartments - C32020 H12021 H1About 6–12 months lateTarget sourceDLD 100% record #1884
  5. The Pulse Boulevard Apartments-C12020 H12021 H1About 6–12 months lateTarget sourceDLD 100% record #1828
  6. The Pulse Residence2019 H12020 H1About 6–12 months lateTarget sourceDLD 100% record #1805
  7. The Pulse Residence Icon2020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1829
  8. The Pulse Residence Park2020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1830
  9. The Pulse Residence Plaza2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1883
  10. The Pulse Townhouses2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1804
  11. The Pulse Villas2023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #1944
  12. The Pulse Villas 22024 H12024 H1Same half-yearTarget sourceDLD 100% record #2279
  13. The Pulse- Beachfront2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2306

Read delivery history project by project

  1. Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
  2. Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
  3. Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?

No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.

Is the developer with the most early entries the safest?

This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.

Return to project-level research