DELIVERY RECORDS · DUBAI
Ellington Properties Project Handover Comparisons
Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.Explore Ellington Properties's company profile and catalogue projects ↗
16 half-year comparisons · 0 additional completed-project records. Original comparison research: 31 Aug 2026.
- Belgravia2017 H12017 H1Same half-yearTarget sourceDLD 100% record #1713
- Belgravia 22019 H12019 H1Same half-yearTarget sourceDLD 100% record #1820
- Belgravia Heights I2022 H22022 H2Same half-yearTarget sourceDLD 100% record #2011
- Belgravia Heights II2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2064
- Belgravia III2021 H22021 H2Same half-yearTarget sourceDLD 100% record #1922
- Belgravia Square2023 H22023 H2Same half-yearTarget sourceDLD 100% record #2100
- Berkeley Place2024 H22024 H2Same half-yearTarget sourceDLD 100% record #2417
- Dt 12020 H12020 H2About 0–6 months lateTarget sourceDLD 100% record #1797
- Eaton Place2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1871
- Hamilton House2025 H12025 H1Same half-yearTarget sourceDLD 100% record #2538
- Harrington House2022 H22022 H2Same half-yearTarget sourceDLD 100% record #2277
- Kensington Waters2024 H12025 H1About 6–12 months lateTarget sourceDLD 100% record #2300
- Oakley Square Residences2023 H22024 H2About 6–12 months lateTarget sourceDLD 100% record #2304
- Somerset Mews2018 H12018 H2About 0–6 months lateTarget sourceDLD 100% record #1981
- Wilton Park Residences2023 H12023 H2About 0–6 months lateTarget sourceDLD 100% record #2158
- Wilton Terraces2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1970
Read delivery history project by project
- Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
- Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
- Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?
No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.
Is the developer with the most early entries the safest?
This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.