DAMAC Properties Project Handover Comparisons

Explore available completion records and compare sourced target and technical-completion periods in six-month bands. Additional completed projects without comparable dates are listed separately. This is not the developer's complete project inventory or a developer rating.

Explore DAMAC Properties's company profile and catalogue projects ↗
91 half-year comparisons · 17 additional completed-project records. Original comparison research: 31 Aug 2026.

EarlierSame half-year0–6 months late6–12 months late12+ months late
ProjectAvailable delivery targetDLD 100% technical completionApproximate differenceSources
  1. Avanti Tower2018 H22018 H2Same half-yearTarget sourceDLD 100% record #1506
  2. Aykon City2022 H12023 H2About 12–18 months lateTarget sourceDLD 100% record #1726
  3. Aykon City 22022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #1746
  4. Bay'S Edge2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1345
  5. Celestia2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1487
  6. Damac Heights2018 H12018 H1Same half-yearTarget sourceDLD 100% record #430
  7. Damac Hills - Artesia2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1523
  8. Damac Hills - Brookfield-12016 H22016 H2Same half-yearTarget sourceDLD 100% record #1349
  9. Damac Hills - Brookfield-22017 H22019 H1About 12–18 months lateTarget sourceDLD 100% record #1347
  10. Damac Hills - Brookfield-32014 H22019 H1About 48–54 months lateTarget sourceDLD 100% record #1356
  11. Damac Hills - Calero2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1593
  12. Damac Hills - Carson2021 H22022 H1About 0–6 months lateTarget sourceDLD 100% record #1620
  13. Damac Hills - Golf Gate2024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2358
  14. Damac Hills - Golf Horizon2015 H22016 H1About 0–6 months lateTarget sourceDLD 100% record #1363
  15. Damac Hills - Golf Panorama2015 H22016 H1About 0–6 months lateTarget sourceDLD 100% record #1359
  16. Damac Hills - Golf Promenade2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1504
  17. Damac Hills - Golf Terrace2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1365
  18. Damac Hills - Golf Veduta2016 H12016 H2About 0–6 months lateTarget sourceDLD 100% record #1364
  19. Damac Hills - Golf Vista2015 H22016 H1About 0–6 months lateTarget sourceDLD 100% record #1362
  20. Damac Hills - Golf Vita2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1932
  21. Damac Hills - Jasmine2018 H22018 H2Same half-yearTarget sourceDLD 100% record #1414
  22. Damac Hills - Longview2018 H22019 H1About 0–6 months lateTarget sourceDLD 100% record #1408
  23. Damac Hills - Loreto2017 H22017 H2Same half-yearTarget sourceDLD 100% record #1508
  24. Damac Hills - Orchid2018 H22018 H2Same half-yearTarget sourceDLD 100% record #1413
  25. Damac Hills - Phoenix2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1412
  26. Damac Hills - Piccadilly Green2018 H12018 H1Same half-yearTarget sourceDLD 100% record #1357
  27. Damac Hills - Queens Meadow2014 H22017 H1About 24–30 months lateTarget sourceDLD 100% record #1355
  28. Damac Hills - Richmond2018 H22018 H2Same half-yearTarget sourceDLD 100% record #1395
  29. Damac Hills - Rochester2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1410
  30. Damac Hills - Rockwood2018 H12018 H1Same half-yearTarget sourceDLD 100% record #1396
  31. Damac Hills - Silver Springs2016 H22016 H2Same half-yearTarget sourceDLD 100% record #1354
  32. Damac Hills - Silver Springs 22019 H12019 H1Same half-yearTarget sourceDLD 100% record #1872
  33. Damac Hills - Silver Springs 32024 H12025 H1About 6–12 months lateTarget sourceDLD 100% record #2228
  34. Damac Hills - The Field2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1389
  35. Damac Hills - The Flora2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1388
  36. Damac Hills - The Trump Estates2016 H12020 H1About 42–48 months lateTarget sourceDLD 100% record #1409
  37. Damac Hills - The Trump Estates 22022 H12022 H1Same half-yearTarget sourceDLD 100% record #2143
  38. Damac Hills - The Trump Estates 32022 H12022 H1Same half-yearTarget sourceDLD 100% record #2160
  39. Damac Hills - The Turf2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1387
  40. Damac Hills - Topanga2018 H12018 H2About 0–6 months lateTarget sourceDLD 100% record #1397
  41. Damac Hills - Trinity2018 H22018 H2Same half-yearTarget sourceDLD 100% record #1407
  42. Damac Hills - Whitefield2016 H12016 H2About 0–6 months lateTarget sourceDLD 100% record #1348
  43. Damac Hills -Whitefield-22014 H22016 H2About 18–24 months lateTarget sourceDLD 100% record #1353
  44. Damac Hills (2) - Acuna2017 H22021 H2About 42–48 months lateTarget sourceDLD 100% record #1622
  45. Damac Hills (2) - Albizia2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1794
  46. Damac Hills (2) - Amargo2022 H22023 H1About 0–6 months lateTarget sourceDLD 100% record #1840
  47. Damac Hills (2) - Amargo 22024 H12024 H1Same half-yearTarget sourceDLD 100% record #2357
  48. Damac Hills (2) - Amazonia2021 H12020 H1EarlierTarget sourceDLD 100% record #1648
  49. Damac Hills (2) - Amazonia-Ex2021 H12021 H2About 0–6 months lateTarget sourceDLD 100% record #2070
  50. Damac Hills (2) - Aquilegia2022 H22022 H2Same half-yearTarget sourceDLD 100% record #1943
  51. Damac Hills (2) - Aster2021 H22021 H2Same half-yearTarget sourceDLD 100% record #1577
  52. Damac Hills (2) - Avencia2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1839
  53. Damac Hills (2) - Avencia-22021 H22022 H2About 6–12 months lateTarget sourceDLD 100% record #1866
  54. Damac Hills (2) - Basswood2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1803
  55. Damac Hills (2) - Centaury2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1624
  56. Damac Hills (2) - Claret2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1549
  57. Damac Hills (2) - Coursetia2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1578
  58. Damac Hills (2) - Janusia2020 H12021 H1About 6–12 months lateTarget sourceDLD 100% record #1621
  59. Damac Hills (2) - Juniper2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1550
  60. Damac Hills (2) - Mimosa2021 H22021 H2Same half-yearTarget sourceDLD 100% record #1821
  61. Damac Hills (2) - Mulberry2021 H22022 H1About 0–6 months lateTarget sourceDLD 100% record #1679
  62. Damac Hills (2) - Navitas2022 H22022 H2Same half-yearTarget sourceDLD 100% record #1712
  63. Damac Hills (2) - Navitas (A & B)2023 H12023 H1Same half-yearTarget sourceDLD 100% record #2184
  64. Damac Hills (2) - Odora2021 H22022 H2About 6–12 months lateTarget sourceDLD 100% record #1600
  65. Damac Hills (2) - Pacifica2022 H12021 H1EarlierTarget sourceDLD 100% record #1647
  66. Damac Hills (2) - Primrose2020 H22021 H1About 0–6 months lateTarget sourceDLD 100% record #1548
  67. Damac Hills (2) - Sanctnary2019 H12019 H2About 0–6 months lateTarget sourceDLD 100% record #1640
  68. Damac Hills (2) - Sycamore2017 H22021 H1About 36–42 months lateTarget sourceDLD 100% record #1599
  69. Damac Hills (2) - Trixis2021 H12021 H1Same half-yearTarget sourceDLD 100% record #1623
  70. Damac Hills (2) - Vardon2022 H12021 H1EarlierTarget sourceDLD 100% record #1767
  71. Damac Hills (2) - Victoria2022 H22022 H2Same half-yearTarget sourceDLD 100% record #1861
  72. Damac Hills (2) - Victoria 22024 H22025 H1About 0–6 months lateTarget sourceDLD 100% record #2293
  73. Damac Hills (2) - Viridis2023 H12023 H1Same half-yearTarget sourceDLD 100% record #1675
  74. Damac Hills (2) - Zinnia2021 H22022 H1About 0–6 months lateTarget sourceDLD 100% record #1595
  75. Damac Hills- Pelham2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1411
  76. Damac Hills-Bel Air2024 H12025 H1About 6–12 months lateTarget sourceDLD 100% record #2236
  77. Damac Hills-Park Residences 12025 H12025 H1Same half-yearTarget sourceDLD 100% record #1938
  78. Damac Hills-Park Residences 42023 H12024 H2About 12–18 months lateTarget sourceDLD 100% record #1930
  79. Damac Hills-Veneto2022 H22023 H2About 6–12 months lateTarget sourceDLD 100% record #1865
  80. Damac Lagoons - Santorini (1)2025 H22025 H2Same half-yearTarget sourceDLD 100% record #2316
  81. Damac Towers By Paramount2018 H22018 H2Same half-yearTarget sourceDLD 100% record #443
  82. Ghalia2019 H12019 H1Same half-yearTarget sourceDLD 100% record #1505
  83. Merano Tower2020 H12020 H1Same half-yearTarget sourceDLD 100% record #1680
  84. Paramount Tower Hotel & Residences2022 H12021 H2EarlierTarget sourceDLD 100% record #1665
  85. Prive By Damac2019 H22019 H2Same half-yearTarget sourceDLD 100% record #1371
  86. Reva Residences2022 H12022 H1Same half-yearTarget sourceDLD 100% record #2018
  87. Royal Golf Villas2015 H22016 H1About 0–6 months lateTarget sourceDLD 100% record #1539
  88. The Distinction2016 H12017 H1About 6–12 months lateTarget sourceDLD 100% record #1329
  89. Tower 1082019 H12019 H1Same half-yearTarget sourceDLD 100% record #1499
  90. Vera Tower2022 H12022 H1Same half-yearTarget sourceDLD 100% record #1786
  91. Zada Tower2023 H12023 H1Same half-yearTarget sourceDLD 100% record #2155

Additional completed-project records

Marked FINISHED at 100% in the DLD snapshot of 15 Jun 2026. Comparable target and technical-completion periods have not yet been established; no timing category is assigned.

Read delivery history project by project

  1. Open the target-date source before judging the delay. An original archived target and a later revised target answer different questions.
  2. Distinguish technical completion from receiving keys. The recorded 100% DLD inspection period is the endpoint used here.
  3. Use the available history to frame questions about your selected project. Do not treat this curated sample as the developer's complete track record.
Does 'same half-year' mean exactly on time?

No. Dates are grouped into January–June and July–December. Two events in the same half-year can still be months apart. The timing labels are approximate categories, not measured day-level delays.

Is the developer with the most early entries the safest?

This dataset cannot establish that. Coverage differs between developers and may omit projects without comparable evidence. It does not score financial strength, construction quality, defects or future delivery risk.

Return to project-level research